Preventive Maintenance Metrics

FMX PM Performance · Rolling 24-month window · Building 110428
Occurrences: 2982 total · 2068 included · 914 safety-excluded
Last pulled: 2026-09-29 16:02 UTC
← PM tasks · Unplanned metrics →
On-Time Performance

Fair-Rite policy: PM is due within 7 business days after it triggers (weekends and company holidays don't count). The headline rate counts anything completed within that grace as on-time, matching Phil's quarterly KPI methodology.

On-Time Rate
98.7%
2038 of 2064 completed within 7-day grace
Strict (No Grace)
66.6%
1374 of 2064 completed on/before trigger
Open & Overdue
1
past 7-day grace, not yet completed
Total Occurrences
2068
in rolling 24-month window
Volume by Month (24-month trailing)

PM Occurrences Created per Month

Quarter-over-Quarter On-Time Rate

Strict (blue) vs Lenient (green, ≤7d grace)

Completion State Mix (Rolling Window)

Where Every Occurrence Landed

Top 10 Users by Volume
User IDTotalOn TimeOverdueRate
618448 1082 771 311 71.3%
676967 311 235 76 75.6%
683520 173 85 88 49.1%
674956 156 107 49 68.6%
680191 127 46 81 36.2%
617520 106 76 30 71.7%
689372 49 17 32 34.7%
650667 22 9 13 40.9%
617519 17 16 1 94.1%
672115 7 4 3 57.1%
Worst On-Time Tasks (≥4 occurrences)
TaskTotalOn TimeOverdueRate
Inspect Gutters 4 0 4 0.0%
Summer A/C inspection 7 0 7 0.0%
Printer Inspection 8 2 5 25.0%
Inspection and lubrication Mule 4 1 3 25.0%
Generac Quarterly Inspection FR 4 1 2 25.0%
Pellet Transfer Conveyor Inspection 13 5 8 38.5%
Pellet Transfer Conveyor Inspection 13 5 8 38.5%
Erich #1 Lubrication 25 11 14 44.0%
Erich #1 Inspection 25 12 13 48.0%
Air Handler Inspection Office Building #8 FR 25 12 13 48.0%